Client: Power Sector Client
Date: 2013/14 (25 weeks)
Nature of Works: Decommissioning, Remediation, Stabilisation
Contract Value: £2.0m Re-measurable Contract
Soilfix was employed by a leading Power Sector client to undertake decommissioning and remediation works to the former coal stock yard of a closed Power Station in Medway, Kent. This was required as part of a site-wide programme of decommissioning following closure.
Soilfix designed and implemented a multi-disciplinary decommissioning and remediation scheme, including:
All works were completed on programme and budget, with no lost time incidents throughout the contract.