Landfill Slope Remediation & Restoration

Penarth, South Wales

Soilfix carried out treatment and slope re-engineering on a former Council landfill to facilitate a prestigious residential development

 

Client: Crest Nicholson Plc
Date: 2015
Type: Landfill remediation, re-engineering & restoration
Value: £490K

THE CHALLENGE:

The client was developing a site at Penarth Heights overlooking Cardiff Bay. Part of the site had been subject to extensive tipping pre-1970s. The Council Tip was on the side of the hill overlooking Cardiff Bay and was highly unstable presenting a risk of landslide to both the development and an adoptable road.

OUR SOLUTION:

Soilfix implemented a remediation scheme to stabilise the embankment which included:

  • Excavation, classification and processing of landfill wastes to form consistent material streams that could be re-used within the embankment;
  • Classification and processing of construction arisings to make suitable for use in embankment;
  • Lime stabilisation of wet/cohesive soils to improve compaction and structure within the embankment;
  • Precision excavation of detailed profiles on steep incline with restricted access including to tie in with existing re-enforced embankment;
  • Construction of re-enforced embankment using multiple layers of interwoven geo-grid between layers of processed/improved and highly compacted soils;
  • Placing topsoil on steep embankment stabilised with geo-mat and hydroseeded with grass;
  • Construction of new footpath along length of new embankment;
  • Comprehensive geotechnical verification testing and regulatory signoff; and,
  • Health, Safety & Environmental controls within a potentially high risk working environment to meet Crest Nicholson’s stringent requirements.

All works were successfully completed to enable commencement of highway works on-programme with site specific geotechnical requirements met.