Former Aniline Dye Works—Remediation & Enabling

Hounslow

Soilfix were contracted to carry out hydrocarbon hot-spot removal, obstructions removal, soil remediation and development platform preparation

 

Client: Department for Education — DfE (LocatED)
Date: 2023
Type: Soil Remediation & Enabling Works
Value: £1,050,000

THE CHALLENGE:

Remediation and enabling of the 1.1Ha former dye factory site in West London was required to facilitate a mixed-use development including a new special education needs (SEN) School. The former site use meant that there was surface, sub-surface obstructions and foundations that required removal before piling.  Furthermore, removal of a large hotspot contaminated with hydrocarbons was also required.

A sustainable remediation solution was required by the client, to create a geotechnically suitable development platform to its D&B Contractor’s construction formation levels, with off-site disposal reduced to a practicable minimum.

OUR SOLUTION:

Soilfix designed and implemented the following complex remediation & enabling works scheme over a 14-week period, fully in accordance with CL:AIRE Code of Practice:

  • Controlled demolition of perimeter wall and installation of perimeter site hoarding;
  • Bulk excavation of materials in accordance with the cut and fill model, along with associated materials management. Approximately 12,500m3 of material was excavated;
  • Slab-breakout and proof dig down to natural subsoils or to 2m from original ground level to remove obstructions left from former infrastructure;
  • Screening and sorting of approximately 4,250m3 excavated made ground;
  • Re-use of suitable materials to reinstate excavated areas to agreed levels;
  • Hotspot excavation and off-site treatment of hydrocarbon impacted soils fully in accordance with Duty of Care;
  • Off-site disposal of contaminated water from hotspot excavation;
  • Exhaustive environmental monitoring and controls, continually communicating with key stakeholders;
  • Segregation of natural subsoil for future re-use as a landscaping capping material; and,
  • Placement of 6F2 crush running layer across site to form a piling / development platform layer.

Soilfix successfully completed all works to budget and on programme with zero lost time accidents, enabling timely sign-off of the remediation strategy and achieving  >98% materials re-use.

 

 

 