Former Rail Depot, Metal Works & Motor Garage/Showroom

Plaistow, East London

Soilfix were contracted to carry out Decontamination, Demolition & Remediation works to enable a mixed Education / Residential Development

 

Client: Confidential
Date: 2021
Type: Decontamination, Demolition, Remediation & Enabling Works
Value: £1.6M

The Challenge

Comprehensive remediation of two free-phase hydrocarbon source areas was required to mitigate risks to residents in neighbouring properties and future site occupants. Further challenges included archaeological constraints, sporadic asbestos-containing materials within the Made Ground, Japanese Knotweed infestation and the site being situated directly adjacent to a London Underground line (LUL) & Station.

Our Solution

Soilfix designed and implemented the following solution, fully in line with LUL requirements, as well as current legislation & Codes of Practice for managing Asbestos, Waste & redundant fuel infrastructure:

  • Procurement and supervision of demolition contractor to undertake demolition works including complex licensed asbestos removal;
  • Decontamination/removal of redundant fuel /oil USTs and associated infrastructure;
  • Controlled slab breakout and targeted obstructions removal (up to 2mbgl). Processing of clean hardcore materials to produce recycled aggregate for re-use as a working platform;
  • Targeted remediation of Japanese knotweed & installation of a boundary root barrier;
  • Surgical excavation of hydrocarbon source area adjacent to railway line, with ex-situ bioremediation treatment of 1,200m3 grossly impacted soils for re-use;
  • Larger heavy-oil LNAPL source area subjected to combined ex-situ / in-situ remediation—horizontal LNAPL recovery trenches advanced into Terrace Gravels for enhanced pumping & treatment from the smear zone;
  • LNAPL recovery enhanced using surfactant enhancement using staged RegenOx PetroCleanze™ injection; and,
  • Residual betterment of groundwater concentrations implemented in both source areas using mixing/injection of Oxygen Release Compounds into the saturated zone; and,
  • Site re-graded and capped with site-won recycled 6F2 material.

Soilfix successfully completed site works with zero lost time accidents.  By adopting a sustainable, risk-based approach in collaboration with the project Consultants (Ramboll UK) using combined in-situ/ex-situ techniques over 12,000 tonnes of hazardous waste was diverted from landfill, keeping 2,400 HGV movements off the congested London road network.

 

Jamie Mitchell Soilfix

Talk to our team

Jamie Mitchell
Pre-Construction Manager

Our projects